Yasuni (01.01.2014 to 03.31.2014)

You are here

PDF versionPDF version
Year: 
2014
Quarter: 
January - March
Communications activities: 

 None

Unusual Events at the TEAM Site: 

 None

New Species: 

 None

Protocol Activities: 
Vegetation: census of the six 1-ha plots completed. Botanical vouchers are now being identified. The vegetation database will be uploaded to TEAM´s portal by the end of April.
Fauna: First array completed. Second array being installed at the moment.
Climate: Weather station running ok.
 
Protocol Problems: 

 None

Schedule Problems: 

 None

Logistical Problems: 

 None