Communications activities: 

There is not communication activities at the site in this sampling period since we had finished all sampling protocols in May 2016.

Unusual Events at the TEAM Site: 

There were no unusual events at the site in this sampling period since we had finished all sampling protocols in May 2016.

New Species: 

There is no new species at the site in this sampling period since we finished all sampling protocols in May 2016.

Protocol Activities: 

From May 2016 up until August 2016, we continued the collection of climate data monthly.

Protocol Problems: 

From August 2016 on, we have several problems with the climate station. Data are not downloading completelly from the datalogger.

Schedule Problems: 

We have had some logistic problems to go visit the climate station due to problems of motorcycle damage. This is a remote place with very bad roads and practically every visit to the climate station requires motorcycle reparations after. Since all expenses from the budget were used until May, we cant fix the motorcycle.

Logistical Problems: 

The same problem explained in the item before.

Suggestions: 

There are no suggestions at this time.