Communications activities: 

F. Rovero met the new warden of Udzungwa NP and introduced her to TEAM project.

Unusual Events at the TEAM Site: 

None

New Species: 

None

Protocol Problems: 

None.

Schedule Problems: 

Climate protocol delayed due to the need of upgrading the equipment.

Logistical Problems: 

The new climate equipment will be installed by the end of August 2010. For a period of 3-6 months, there will be a transitional configuration with old and new systems running together, for calibration.