Nouabalé Ndoki (07.01.2013 to 09.30.2013)

You are here

PDF versionPDF version
Year: 
2013
Quarter: 
July - September
Communications activities: 

Nouabalé-Ndoki is in its fourth year of field deployment. Vertebrate and vegetation sampling will begin in November 26th, 2013. The TEAM team met on the 29th October to discuss about the next VG and Camera trap field mission.

One of the Data Collectors is leaving the project for 18 months for studies purpose, and a new one is being trained for the next sampling season.

Unusual Events at the TEAM Site: 

None

New Species: 

None

Protocol Activities: 

No VG or Camera trap field work during the last 3 months.

The climate station is experiencing a power issue problem with the fan often off. To solve the problem, the data logger operating system will be update in the next few days.

Protocol Problems: 

The climate station is experiencing a power issue problem with the fan often off. To solve the problem, the data logger operating system will be updated in the next few days.

Schedule Problems: 

None

Logistical Problems: 

None

Suggestions: 

None