Communications activities: 

No specific communication activities at the site during this quarter.

Unusual Events at the TEAM Site: 

No unusual climatic events at the Nam Kading site this quater

New Species: 

No new species discovered at the site this quarter.

 

 

Protocol Activities: 

During this quarter the vegetation monitoring team completed three plots (5, 1, 2). In each plot 496, 520, and 547 stems were measured respectively. 

During this quarter the terestrial vertebrate monitoring team deployed and collected 30 camera traps from Arrays 2 and 3.

During this quarter the climate monitoring team continued to implement the protocol according to the TEAM standard.

Protocol Problems: 

No major problems with the protocol implementation at this time

Schedule Problems: 

No schedule problems at this time

Logistical Problems: 

No logicitical problems at this time.

Suggestions: 

No suggestions at this time